Question 30
In a service provider network, a company has an existing IP address scheme. Company A’s network currently uses the
following scheme:
Company b uses the following scheme:
Subnet 1: 192.168.1.50/28
The network administrator cannot force the customer to update its IP scheme. Considering this, which of the following is the
BEST way for the company to connect these networks?
A. DMZ
B. PAT
C. NAT
D. VLAN
Correct Answer: C
-
-
-
Question 31
A network engineer is designing a new network for a remote site. The remote site consists of ten desktop computers, ten VoIP
phones, and two network printers. In addition, two of the desktop computers at the remote site will be used by managers who
should be on a separate network from the other eight computers. Which of the following represents the BEST configuration for
the remote site?
A. One router connected to one 24-port switch configured with three VLANS: one for the manager’s computers and
printer,one for the other computers and printer, and one for the VoIP phones
B. Two routers with each router connected to a 12-port switch, with a firewall connected to the switch connected to
themanager’s desktop computers, VoIP phones, and printer
C. One router connected to one 12-port switch configured for the manager’s computers, phones, and printer, and one 12-
portswitch configured for the other computers, VoIP phones, and printer
D. One router connected to one 24-port switch configured with two VLANS: one for the manager’s computers, VoIP
phones,and printer, and one for the other computers, VoIP phones, and printer
Correct Answer: A
-
-
Question 32
A network technician is troubleshooting an end-user connectivity problem. The network technician goes to the appropriate IDF
but is unable to identify the appropriate cable due to poor labeling. Which of the following should the network technician use to
help identify the appropriate cable?
A. Tone generator
B. Multimeter
C. OTDR
D. Loopback adapter
Correct Answer: A
-
-